Post-treatment calculator

UV Disinfection Sizing & Chlorination Contact-Time Calculator

Use two separate preliminary design calculators for MBR permeate disinfection: a vendor-validated UV-reactor sizing calculation and a chlorination CT/contact-basin mass balance.

Preliminary design tool only. Do not use illustrative UV intensity × time arithmetic to claim a validated dose or pathogen-log credit. Do not use a generic CT target to establish chlorination compliance. Select UV reactor duty points, CT targets, chlorine residuals, and operating envelopes from the applicable permit, water/reuse objective, site testing, and validated equipment documentation.
Used only to label chlorine-product cost outputs; no currency conversion is applied.
1

UV Disinfection Sizing

Size duty and standby reactors at a specified vendor-validated capacity, target dose, and minimum UV transmittance.

UV sizing inputs

The validated capacity must be from the selected reactor at the entered dose and UVT condition.

m³/d annual-average permeate flow
peak ÷ average flow
mJ/cm²; set by target/reuse basis
% UVT at 254 nm; use design minimum
m³/h at entered UVT and dose
installed N+standby arrangement
kW; vendor input for preliminary energy estimate
days/year
mW/cm²; not a validation input
seconds; not a validation input
% multiplier for the illustration only; validated manufacturer curves govern design.

UV sizing results

Primary capacity results use the vendor-validated reactor duty point.

Peak design flow
62.5m³/h
1,500 m³/d
Duty reactors
2units
60.0 m³/h each
Installed reactors
3units
2 duty + 1 standby
Duty train capacity
120.0m³/h
52.1% peak utilization
Minimum UVT documented
65.0%
Entered design condition
Target validated dose
40.0mJ/cm²
Permit/reuse basis input
Illustrative fluence
43.2mJ/cm²
Not a validation result
Illustrative dose margin
3.2mJ/cm²
Arithmetic screen passes
Preliminary electrical energy
52,560kWh/y
2 duty × 3.0 kW
UV design boundary: The illustrative arithmetic is above the entered target dose, but it is not a validation result.
2

Chlorination Contact-Time & Chemical-Dosing Screen

Screen chlorine product demand and the contact basin using peak flow, outlet residual, and a transparent T10/baffling-factor approach.

Chlorination and CT inputs

Use the outlet residual and a permit- or target-specific CT requirement; do not substitute the default screening values for compliance.

m³/d; used for average chemical demand
used for contact-time screen
mg/L as available Cl₂; site-test input
mg/L as available Cl₂ at basin outlet
mg·min/L; set by permit/pathogen/pH/temperature basis
m³ at minimum operating level
use tracer-tested factor when available
% active by mass; editable product input
kg/L; use supplied data sheet
days/year
days of average product demand
percent above coverage demand
currency/kg commercial product

Chlorination contact-time results

The contact-time test uses peak hydraulic flow and the selected outlet residual.

Total chlorine dose
5.00mg/L
4.00 demand + 1.00 residual
Active chlorine demand
5.00kg/d
Average flow basis
Product volume
33.3L/d
12.5% available chlorine
Peak product pump screen
2.08L/h
Continuous peak-flow equivalent
Theoretical detention time
96.0min
100.0 m³ at peak flow
Effective T10
48.0min
T × 0.50 baffling factor
CT achieved
48.0mg·min/L
At/above screening target
Required contact volume
62.5
30.0 mg·min/L target CT
Contact-volume margin
37.5
Available − required
Nominal product storage
1,150L
30 days + 15%
Annual product volume
12,167L/y
365 operating days
Annual product cost
USD 14,600
Commercial product only
CT screening result: The entered contact volume, peak flow, residual, and baffling factor meet the entered screening CT target.

Governing formulas

UV validated-reactor sizing

Peak flow = Average permeate flow × Peak-flow factor
Duty reactors = ceiling(Peak flow, m³/h ÷ Validated capacity per reactor)
Installed reactors = Duty reactors + Standby reactors
Illustrative fluence = Effective intensity × Exposure time × Availability factor

The illustrative fluence is shown only to make the intensity/time relationship transparent. Reactor capacity is sized from the entered validated operating point; a simple intensity × time estimate cannot replace reactor validation.

Chlorination dose, T10, and CT

Chlorine dose = Chlorine demand + Outlet residual
Theoretical detention time, T = Contact volume ÷ Peak flow
T10 = T × Baffling factor
CT achieved = Outlet residual × T10
Required contact volume = Peak flow × [Target CT ÷ Outlet residual ÷ Baffling factor]

Daily product demand uses average flow; the displayed peak product flow is a continuous equivalent pump-rate screen. Confirm actual chemical-feed turndown, residual decay, mixing, and dosing control with plant data and the supplier.